Bourne ISWM Projects Advance on Schedule
Two major Bourne building projects continued advancing on their original construction schedules.
Two major Bourne building projects continued advancing on their original construction schedules.
ISWM Building Committee unanimously voted to increase waste facility push wall to 16 feet, removing a design step. Peter J Meier moved, seconded by Thomas Joyce; all five present voted yes: Asa Mintz (Chair), Gregory Siroonian (Vice Chair), Thomas Joyce (Clerk), Nolan LeRoy, and Peter J Meier.
The ISWM Building Committee approved $1,060,283.70 in invoices for ongoing construction. Chair Asa Mintz led the committee in unanimous votes on three invoices from Pomroy Associates ($10,680 and $35,282.40) and Page Building and Construction ($1,014,321.30).
ISWM Building Committee voted to move the Waste Management Facility from schematic design to design development, with an estimated construction cost around $15 million.
Building Committee approves $84,688 in design invoices for two town facilities.
ISWM Building Committee unanimously accepts May 18 as Notice to Proceed date for Office and Maintenance Garage. Vice Chair Gregory Siroonian and three members present approved the construction kickoff date and endorsed three invoices totaling $90,063.65, including engineering work from Weston and
ISWM Building Committee advances two major projects. The committee voted 3-1, with Gregory Siroonian abstaining, to recommend Page Building Construction to the Town Administrator after the firm bid one million dollars below the advertised estimate for the Office and Maintenance Garage. Chairman Asa
ISWM Building Committee approves $65,247.50 in invoices ahead of general contractor bids. Chairman Asa Mintz's panel voted unanimously to approve $52,747.50 for Office and Maintenance Garage OPM Services and $12,500 for the Transfer Station. The Office and Maintenance Garage project will receive
ISWM Building Committee advances office garage to bidding. Chair Asa Mintz and the committee unanimously approved construction documents and prequalifications for 16 general contractors and 97 sub-contractors on January 13th. Bid documents release January 28th with general bids due March 5th at 2